January Report
- Report Date
- January 2017
Achievements in Last Period
- Access to SharePoint Site given to Production Management Team Leads In Application Management and Technology Management
- Structure for Technical Architecture Documentation created, ready for latest version of TADs to be uploaded to SharePoint
- Agreed with Project Sponsor that updates to Draft Disaster Recovery Plan to be completed out with the project to allow project to close
Issues
- Estimated that there will be circa. 15 days unspent resource effort returned to the INF Programme on project closure as per agreement with Programme Manager and Project Sponsor, a PICCL has been raised ready for submitting for approval on project closure.
Next Steps
- Update Deployment Checklist template to include changes to storage of TAD on projects website
- Agree completion report and close project
The project status is GREEN
| 14-Feb-2017 | Delivery Complete |
| 21-Feb-2017 | Closure |
- Approved budget
- 75.0 days
- Activity this month
- 2.0 days
- Activity this year
- 16.2 days
- Activity to date
- 33.3 days
- Estimate to complete current year
- 4.5 days
- Estimate to complete future years
- 0.0 days