Report for May 2016

Report Date
May 2016

Achievements in Last Period

  • Completed upgrade of CITESTER dev, beta, test and live CITESTER to CF11
  • Project Closed

Issues

Target dateTitle
19-May-2016Closure
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
29.0 days
Activity this month
2.1 days
Activity this year
14.5 days
Activity to date
14.5 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Bamboo Upgrade 2016
Code
INF117
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
Gillian Henderson
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
18-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
26-May-2016
Programme Priority
10
Overall Priority
Normal
Category
Compliance