Report for April 2016
- Report Date
- April 2016
Achievements in Last Period
- Environment setup for dev,beta, test and live CITESTER migrations
- Started upgrade of CITESTER dev environment to CF11.
Issues
- Issue getting Dev Team and Dev Tech resources to complete the CITESTER migrations. See PICCL 2 (https://www.projects.ed.ac.uk/project/inf117/issues/2)
- CITESTER and Closure Milestones moved as a consequence (however the main project objectives achived as Bamboo upgrade complete)
Next Steps
- Complete upgrade of CITESTER dev environment.
- Upgrade beta, test and live CITESTER to CF11
- Closure
Target date Title 12-May-2016 CITESTER (dev,beta, test and live) Upgraded 19-May-2016 Closure
- Approved budget
- 29.0 days
- Activity this month
- 0.8 days
- Activity this year
- 12.1 days
- Activity to date
- 12.1 days
- Estimate to complete current year
- 9.9 days
- Estimate to complete future years
- 0.0 days