Report for February 2017

Report Date
February 2017

 

Project closure agreed in the last reporting period. 

Closure document can be found here; 

https://www.projects.ed.ac.uk/project/inf116/completion-report

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
29.0 days
Activity this month
0.5 days
Activity this year
14.0 days
Activity to date
29.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ASTA Upgrade 15/16
Code
INF116
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Nikki Stuart
Project Sponsor
Rhian Davies
Current Stage
Close
Status
Closed
Start Date
17-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Mar-2017
Programme Priority
10
Overall Priority
Normal
Category
Compliance

Documentation