Report for February 2017
- Report Date
- February 2017
Project closure agreed in the last reporting period.
Closure document can be found here;
https://www.projects.ed.ac.uk/project/inf116/completion-report
- Approved budget
- 29.0 days
- Activity this month
- 0.5 days
- Activity this year
- 14.0 days
- Activity to date
- 29.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days