Report for December 2016
- Report Date
- December 2016
Achievements:
- TEST and LIVE software updated to resolve issue with intermittent unplanned outages.
Issues:
- None
Next Steps:
- Decommission any old versions of the software
- Handover to Tech Man
- Deployment sign off
- Closure
Milestones
| 20-Jan-2017 | Deployment Sign Off |
| 17-Feb-2017 | Project Closure |
- Approved budget
- 37.0 days
- Activity this month
- 3.0 days
- Activity this year
- 13.0 days
- Activity to date
- 25.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days