Current project status Report Date RAG Budget Effort Completed Effort to complete February 2017 BLUE 29.0 days 29.0 days 0.0 Content Status Closed Current Stage Close Start Date Wednesday, 17 February 2016 Close Date Friday, 3 March 2017 Project information Project Code INF116 Programme ISG - IS Applications Infrastructure (INF) Session 16/17 15/16 Organisational Unit IS Applications Project Management Office (if relevant) ISG PMO Project Category Compliance Programme Priority 10 Overall Priority Normal