Report for September 2014

Report Date
September 2014

Achievements in Last Period

  • Project website set up
  • Initial meetings with Development Technology and Production Management to discuss what needs to be included in project
  • Work started on Project Brief

Issues

  • Planning sign-off moved because of difficulties in getting metting arranged (due to leave & training)

Next Period

  • Project brief to be submitted to WIS

 

Milestones

Target dateTitleStage
17-Oct-2014End of PlanningPlan
27-May-2016DeliveryDeliver
01-Jul-2016ClosureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
260.0 days
Activity this month
4.5 days
Activity this year
4.5 days
Activity to date
4.5 days
Estimate to complete current year
155.5 days
Estimate to complete future years
100.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance