Report for March 2014

Report Date
March 2014

Achievements in Last Period

  • The updated version of the Strategy Document has been approved by the key stakeholder groups.
  • Delivery milestone achieved and project moved to closure.
  • Closure report drafted and submitted for formal closure.

Issues

  • No issues.

Next Steps

  • Close project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
32.0 days
Activity this month
1.0 day
Activity this year
33.0 days
Activity to date
33.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Application Tier Infrastructure Upgrade
Code
INF104
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
Adam Wadee
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
26-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
09-Apr-2014
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation