Report for November 2019
- Report Date
- November 2019
Achievements this Period
- Project brief was approved
- Comms and engagement plan was drafted and is being reviewed by sponsor
- New BA assigned and WAM analysis completed
- Proposed new College WAM distributed to Heads of Schools for review
- Work is underway on the Application and Data Architecture document which will provide the board with the dataflow picture they requested
- Initial analysis for the HR API work is underway which will enable an estimation of the work required to implement
- Initial analysis underway for the TRAC code review deliverable
Issues
- Although the issue raised last month about loss of BA to Core Systems programme has now been resolved, it has delayed the project by 3 weeks. This delay may be compounded by the industrial action as the Heads of School may not be able to complete College WAM review by the requested date.
Next Steps
- Finalise comms and engagement plan and share with Board
- Review Head of School responses to proposed College WAM due by 13th December
- Finalise analysis and produce estimate for the HR API work (including BI team documenting issues/barriers with current manual process
- Project milestones to be revised once Head of School responses have been reviewed and the level of variance is understood
Milestones
- Approved budget
- 85.0 days
- Activity this month
- 12.0 days
- Activity this year
- 22.5 days
- Activity to date
- 22.5 days
- Estimate to complete current year
- 66.0 days
- Estimate to complete future years
- 0.0 days