Report for October 2019

Report Date
October 2019

Achievements in this Period

  • Inaugural Project Board meeting (this was rescheduled which has slightly delayed brief sign-off)
  • Project Brief reviewed with Board
  • Brief updated with feedback from Board
  • Replacement BA recruited and assigned to start work on project on 05/11/19

Issues

BA assigned to project was reassigned to Core Systems

Next Steps

  • Complete approval of Brief by Board and submit to WIS
  • Complete handover to new BA
  • Draft project's communication and engagement strategy for review at next Board meeting

 

Milestones

Brief approval was slightly delayed due to Board meeting being rescheduled. Being completed w/c 4th November.

Stage Milestone Due Date Complete
Plan Project brief approval 10-Oct-2019 No
Execute Project Board approval of Communications Plan and engagement strategy to delivery 18-Nov-2019 No
Analyse Completion of API analysis and estimation to current Oracle HR 22-Nov-2019 No
Analyse Completion of Business Analysis - updated College WAM 29-Nov-2019 No
Execute Project Board approval of updated College WAM 16-Dec-2019 No
Execute WAM Co-ordinators forum organisation established 31-Jan-2020 No
Deliver Approved revised College WAM implemented in Simitive 31-Jan-2020 No
Execute Head of Subject Area Simitive training completed 28-Feb-2020 No
Deliver API established with current HR system 28-Feb-2020 No
Deliver Project Delivery 31-Mar-2020 No
Deliver Cutover plan in place with Core Systems Implementation project 30-Apr-2020 No
Deliver Sustainment of WAMS use checkpoint pre-closure 29-May-2020 No
Deliver Completion of cutover to new Core System 08-Jun-2020 No
Deliver Completion of enagagment work to ensure sustainment of WAMs use 10-Jul-2020 No
Close Project Closure approved 31-Jul-2020 No
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Project has been given an overall RAG of AMBER, reflecting the AMBER status against Time. This is because it is likely that a delay may occur in the completion of the Business Analysis due to the loss of the resource to the Core Systems Programme. A new BA has been assigned and handover has taken place.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
75.0 days
Activity this month
6.2 days
Activity this year
10.4 days
Activity to date
10.4 days
Estimate to complete current year
74.0 days
Estimate to complete future years
0.0 days

Project Info

Project
WAMS Business Embedding
Code
HSS031
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Fraser Muir
Current Stage
Analyse
Status
In Progress
Project Classification
Grow
Start Date
23-Sep-2019
Planning Date
10-Oct-2019
Delivery Date
31-Mar-2020
Close Date
31-Jul-2020
Overall Priority
Normal
Category
Discretionary