Report for December 2019
- Report Date
- December 2019
Achievements
- Planned a governance meeting in early January
Issues
- No issues
Next Steps
- Project team to discuss options with Students Association to agree how to have more student engagement in semester 2
- Track the weekly usage of the pilot in Learn and Teams in semester 2
- Students Association to ask the reps to seed the discussion with questions or updates
- Agree revised suspension date with project team in January
- Agree with project team when the evaluation will take place
| Stage | Milestone | Date |
| Execute | Suspension of Project | 24-Jan-2020 |
| Execute | Unsuspend | 22-May-2020 |
| Execute | Semester 2 Pilot End | 05-Jun-2020 |
| Deliver | Deliver Report recommendations | 12-Jun-2020 |
| Deliver | Sign off Report recommendations (Major) | 19-Jun-2020 |
| Close | Closure of Project (Major) | 30-Jun-2020 |
- Approved budget
- 30.0 days
- Activity this month
- 1.0 day
- Activity this year
- 13.0 days
- Activity to date
- 24.0 days
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 0.0 days