Monthly Project Report
- Report Date
- November 2019
Achievements
- Pilot has officially started at end of week 8 when the reps received their demo from Teams and Learn
- Student Association held the pilot reps briefings
- Pilot officially started 8-Nov-2019
- Semester 1 has little time left to gain benefit of uptake
- At end of week 9 (15-Nov) we have the figures from Learn
-
The Learn update!
42% and 41% have logged in to Accounting & Finance and Structural Engineering with Architecture respectively and 26% have logged into MSc International Animal Welfare, Ethics and Law
-
Issues
- No issues
Next Steps
- Track the weekly usage of the pilot in Learn and Teams
- Students Association to ask the reps to seed the discussion with questions or updates
- Agree revised suspension date with project team in January
- Agree with project team when the evaluation will take place
| Stag | Milestone | ||||
| Execute | Semester 1 Pilot End | 20-Dec-2019 | No date available | No | |
| Execute | Suspension of Project | 24-Jan-2020 | 22-Nov-2019 | No | |
| Execute | Unsuspend | 22-May-2020 | No date available | No | |
| Execute | Semester 2 Pilot End | 05-Jun-2020 | No date available | No | |
| Deliver | Deliver Report recommendations | 12-Jun-2020 | No date available | No | |
| Deliver | Sign off Report recommendations (Major) | 19-Jun-2020 | No date available | No | |
| Close | Closure of Project (Major) | 30-Jun-2020 | No date available | No |
- Approved budget
- 30.0 days
- Activity this month
- 1.0 day
- Activity this year
- 12.0 days
- Activity to date
- 23.0 days
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 0.0 days