Report for September 2019

Report Date
September 2019

Achievements

  • Final versions of documentation approved by all stakeholders
  • Deliverables signed off and agreement that project can now close

Issues

  • Short delay so that feedback from TaD Working Group (including external partners) coud be incorporated into final versions

Next steps

  • Close project

Milestones

 

Stage Milestone Due Date
Close Project Closure 27-Sep-2019

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
86.0 days
Activity this month
2.6 days
Activity this year
7.1 days
Activity to date
90.3 days
Estimate to complete current year
0.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Scoping and Options Analysis for Scottish Archival Resources Online
Code
HSS028
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
05-Nov-2018
Planning Date
18-Jan-2019
Delivery Date
13-Sep-2019
Close Date
18-Oct-2019
Overall Priority
Normal
Category
Discretionary

Documentation