HSS013: LO Grade Reporting
- Report Date
- May 2016
Achievements this period
Project Brief signed off/WIS approved
Test scripts written
2wkly team meetings issued to review progress and address R&I's
System Design commenced
Issues
NONE
Next Steps
Complete SDS
SDS Sign Off
Commence development of Student/Staff/Desktop Export
Milestones
Target date | Title | Complete |
06/05/16 | Planning | YES |
29/07/16 | Delivery | NO |
29/08/16 | Closure | NO |
- Approved budget
- 56.0 days
- Activity this month
- 7.3 days
- Activity this year
- 17.4 days
- Activity to date
- 17.4 days
- Estimate to complete current year
- 32.3 days
- Estimate to complete future years
- 6.3 days