HSS013: LO Grade Reporting

Report Date
May 2016

Achievements this period

Project Brief signed off/WIS approved

Test scripts written

2wkly team meetings issued to review progress and address R&I's

System Design commenced

Issues

NONE

Next Steps

Complete SDS

SDS Sign Off

Commence development of Student/Staff/Desktop Export

Milestones

Target date

Title

Complete

06/05/16

Planning

YES

29/07/16

Delivery

NO

29/08/16

Closure

NO

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
56.0 days
Activity this month
7.3 days
Activity this year
17.4 days
Activity to date
17.4 days
Estimate to complete current year
32.3 days
Estimate to complete future years
6.3 days

Project Info

Project
LO Grade Reporting
Code
HSS013
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Nikki Hackett Reed
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
19-Aug-2016
Programme Priority
3
Overall Priority
Normal