HSS013: LO Grade Reporting
- Report Date
- April 2016
Achievements this period
An initial meeting with Olwen and Alex to introduce myself and have a quick review of the project objectives.
A meeting with Geir and Myles to introduce myself and review the outline project brief and estimations based on our understandings.
Project Plan drafted
3 Point Estimate drafted
Requirements Definitions Workshop with key stakeholders to collectively agree specifications
Project Brief issued for sign off
Issues
Revised Planning Milestone from 29/04 to 06/05 approved by WIS
Next Steps
Create BRD/Sign off
Create SDS/Sign off
Develop Student View/Staff View/Desktop Export
Test scripts written
Milestones
Target date | Previous Date | Title | Complete |
06/05/16 | 29/04/16 | Planning | NO |
12/07/16 | 30/06/16 | Delivery | NO |
10/08/16 | 29/07/16 | Closure | NO |
- Approved budget
- 100.0 days
- Activity this month
- 5.6 days
- Activity this year
- 8.4 days
- Activity to date
- 8.4 days
- Estimate to complete current year
- 53.1 days
- Estimate to complete future years
- 2.8 days