2 wkly team meeting 18/07/16

Hiya Andy, just thought I’d give you a last update before leaving for Athens

  • I have asked Geir for an official sign off of Build to add to the Project Website but nothing received as of yet (I did cc you)– I will keep chasing
  • I have spoken with Anna, apologised for the rushed engagement and added in an extra task for Handover as requested. I’ve worked it so that it doesn’t affect our resourcing in ASTA– she’s cool
  • Between 04/07/16 – 15/07/16 Alex and Myles will be undertaking UAT (Myles in on A/L 13/07 – 01/08)
  • 18/07/16 you will need to chair our ACCEPTANCE SIGN OFF team meeting with the purpose to deploy 20/07 (purely selfish as I don’t return until 19/07)
  • DIAL IN Details: 08447620762            PASS CODE: 16630
  • Apologises to have left this with you. The original plan had been for build and integration to have taken place over this period which meant very little involvement from yourself whilst I was away.  I don’t envisage there being much call on your time but never say never. Thanks for covering.

Project Info

Project
LO Grade Reporting
Code
HSS013
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Nikki Hackett Reed
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
19-Aug-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary