May 2016

Report Date
May 2016

Achievements this period

  • DSOR and Closure achieved

 

Issues

  • None

 

Next Steps

  • Closure has been submitted to WIS for approval on 10/06/16

Note - timesheets outstanding for closure, hence "estimate to complete" is showing 3 days, although project is now closed.

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
26.0 days
Activity this month
5.0 days
Activity this year
22.0 days
Activity to date
22.0 days
Estimate to complete current year
3.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Cesar Update
Code
HSS012
Programme
CAHSS Portfolio Projects
Project Manager
Chris Konczak
Project Sponsor
Jemma Wallace
Current Stage
Close
Status
Closed
Start Date
05-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Jun-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation