April 2016

Report Date
April 2016

Achievements this period

  • New milestone dates entered
  • Business has signed off on UAT.
  • New deployment date assigned 

 

Issues

  • Deployment to LIVE needs to wait until HSS011 is deployed. HSS011 is delayed as waiting on deployment of WPMServe which has had UAT issues to resolve.
  • Project is AMBER as it required milestone changes to keep in line with HSS011 deployment

 

Next Steps

  • Deployment to LIVE
  • DSOR
  • Closure

 

Milestones

05-May-2016Delivery
17-May-2016Deployment sign off
20-May-2016Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
26.0 days
Activity this month
1.0 day
Activity this year
17.0 days
Activity to date
17.0 days
Estimate to complete current year
8.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Cesar Update
Code
HSS012
Programme
CAHSS Portfolio Projects
Project Manager
Chris Konczak
Project Sponsor
Jemma Wallace
Current Stage
Close
Status
Closed
Start Date
05-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Jun-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation