March 2016

Report Date
March 2016

Achievements this period

  • Build work completed for each JIRA, and pushed into TEST
  • Agreement with Applications Management that there is no need for integration testing as this is all managed within the code by using test driven development where each unit is tested on deployment.
  • Now in UAT

 

Issues

  • Deployment to LIVE needs to wait until HSS011 is deployed. This has delayed the original milestones.
  • Time is AMBER due to milestones changes required once HSS011 is deployed. HSS011 is also waiting on a WPMServe deployment, so milestones will be updated once this is known.

 

Next Steps

  • New milestone dates entered
  • UAT signed off.
  • New deployment date assigned 

 

Milestones

28-Mar-2016Acceptance signoff
04-Apr-2016Delivery
18-Apr-2016Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
26.0 days
Activity this month
6.0 days
Activity this year
12.0 days
Activity to date
12.0 days
Estimate to complete current year
13.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Cesar Update
Code
HSS012
Programme
CAHSS Portfolio Projects
Project Manager
Chris Konczak
Project Sponsor
Jemma Wallace
Current Stage
Close
Status
Closed
Start Date
05-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Jun-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation