March 2016
- Report Date
- March 2016
Achievements this period
- Build work completed for each JIRA, and pushed into TEST
- Agreement with Applications Management that there is no need for integration testing as this is all managed within the code by using test driven development where each unit is tested on deployment.
- Now in UAT
Issues
- Deployment to LIVE needs to wait until HSS011 is deployed. This has delayed the original milestones.
- Time is AMBER due to milestones changes required once HSS011 is deployed. HSS011 is also waiting on a WPMServe deployment, so milestones will be updated once this is known.
Next Steps
- New milestone dates entered
- UAT signed off.
- New deployment date assigned
Milestones
| 28-Mar-2016 | Acceptance signoff |
| 04-Apr-2016 | Delivery |
| 18-Apr-2016 | Closure |
- Approved budget
- 26.0 days
- Activity this month
- 6.0 days
- Activity this year
- 12.0 days
- Activity to date
- 12.0 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 0.0 days