Report for December 2014
- Report Date
- December 2014
Achievements in Last Period
- There was some questions around the technical architecture relating to patching and the HTTP nature of the application. These have been responded to and the project is ready for closure.
- Once the Technical Architecture Document has been updated all parties have agreed to close the project
Issues
- None outstanding
Next Steps
- Close the project
Milestones
| Target date | Title |
|---|---|
| 15-Jan-2015 | Project Closure |
- Approved budget
- 32.0 days
- Activity this month
- 0.9 days
- Activity this year
- 11.4 days
- Activity to date
- 28.2 days
- Estimate to complete current year
- 1.3 days
- Estimate to complete future years
- 0.0 days