May 2015
- Report Date
- May 2015
Report by Andrew Stewart (on behalf of Chris Konczak) for April 2015
Achievements in Last Period
- Meeting regarding outstanding financial reports was held, during which it was agreed that these reports should be undertaken as a separate project
- The project closure report has been prepared and circulated
Issues
- Currently trying to clarify if the reported issue regarding 'Publish' controls for making the courses in CESAR available on the web require to be resolved within teh current project
Next Steps
- Clarify impact of 'Publish' issues
- Complete DSOR sign-off
- Hold Project closure meeting and close project
- Determine strategy with regards additional financial based reports
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days