Report for April 2015
- Report Date
- April 2015
Achievements in Last Period
Meeting about BI issues held, and agreement made to open seperate project for BI
Progress with BI issues
Issues
Continued developer conflicts have held up finishing BI
Next Steps
Get BI from TEST into LIVE
DSOR closure
Project closure
Milestones
| 06-May-2015 | Deployment of BI updates - JIRA 283 |
| 18-May-2015 | Deployment Sign off Review |
| 18-May-2015 | Project Closure |
- Approved budget
- 818.0 days
- Activity this month
- 13.6 days
- Activity this year
- 822.0 days
- Activity to date
- 822.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days