Report for April 2015

Report Date
April 2015

Achievements in Last Period

Meeting about BI issues held, and agreement made to open seperate project for BI

Progress with BI issues

 

Issues

Continued developer conflicts have held up finishing BI

 

Next Steps

Get BI from TEST into LIVE

DSOR closure

Project closure

 

Milestones

06-May-2015Deployment of BI updates - JIRA 283
18-May-2015Deployment Sign off Review
18-May-2015Project Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
818.0 days
Activity this month
13.6 days
Activity this year
822.0 days
Activity to date
822.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
CESAR: New administration platform for OLL
Code
HSS001
Programme
CAHSS Portfolio Projects
Project Manager
Chris Konczak
Project Sponsor
Nicola Davidson
Current Stage
Close
Status
Closed
Start Date
06-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
26-Jun-2015
Programme Priority
1
Overall Priority
Normal
Category
Compliance