Weekly Team Meeting - 14 April 2014

Work completed last week

  • Last of the user stories workshops completed
  • Write up of all user stories completed
  • Commenced de-duplication of user stories
  • TAD Circulated for review
  • Dev environment built

Issues Encountered

  • Only have a Dev environment will need the remaining environments to complete foundation
  • 1,400 user stories noted,it will take a sizable amount of effort to review them all

Upcoming work

  •  eVisitor removal - ready to implement when start build - John/Thalia
  • OLL Book recommendation - need to complete (detail of requirement in piccl log) - John/Thalia
  • Build Beta, Test, Train and Live Environments - Peter/Ewen
  • Review and sign off TAD - All
  • Scope out user security model and potential early start of build - Mike/Chis?
  • Establish minimum viable product - next week (21 April) - All
  • Release planning - next week (21 April) - All
  • Book standup meetings - Craig
  • Book fortnightly planning and prioritisation meetings - Craig

AOB

  • Avoid FIN098 stand up meetings 9:30 to 10:00
  • Attempt to plan releases to avoid UWP007 and FIN098

Project Info

Project
CESAR: New administration platform for OLL
Code
HSS001
Programme
CAHSS Portfolio Projects
Project Manager
Chris Konczak
Project Sponsor
Nicola Davidson
Current Stage
Close
Status
Closed
Start Date
06-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
26-Jun-2015
Programme Priority
1
Overall Priority
Normal
Category
Compliance