Monthly Progress Report
- Report Date
- July 2016
Achievements:
- Deployed to LIVE in July
- Apex work has been completed in Dev
Issues
- None
Next Steps
- Apex work will be progressed to TEST and LIVE
- Start iterative testing in LIVE in August
Milestones
| 30-Sep-2016 | Final HESA return |
| 14-Oct-2016 | Commit |
| 11-Nov-2016 | Final Submission |
| 25-Nov-2016 | Closure |
- Approved budget
- 90.0 days
- Activity this month
- 2.5 days
- Activity this year
- 36.0 days
- Activity to date
- 36.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 50.0 days