Monthly Progress Report

Report Date
July 2016

Achievements:

  • Deployed to LIVE in July
  • Apex work has been completed in Dev

Issues

  • None

Next Steps

  • Apex work will be progressed to TEST and LIVE
  • Start iterative testing in LIVE in August

Milestones

30-Sep-2016Final HESA return
14-Oct-2016Commit
11-Nov-2016Final Submission
25-Nov-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
90.0 days
Activity this month
2.5 days
Activity this year
36.0 days
Activity to date
36.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
50.0 days

Project Info

Project
HESA staff return – 15/16
Code
HRS090
Programme
Human Resources (HRS)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
28-Mar-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
25-Nov-2016
Overall Priority
Normal
Category
Compliance