Monthly Progress Report

Report Date
April 2016

Achievements:

  • Project website set up
  • Project start up meeting took place
  • Brief completed
  • Investigation into HESA requirements
  • Design progressed

Issues

  • None

Next Steps

  • Resourcing for project in progress
  • Familiarisation for contractor when has been successfully obtained 
  • Review design

Milestones

22-Apr-2016Planning
20-May-2016Initial Build
10-Jun-2016Initial Acceptance
29-Jul-2016First Deployment
30-Sep-2016Final HESA return
14-Oct-2016Commit
11-Nov-2016Final Submission
25-Nov-2016Closure

Project has been given a RAG status of Green

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
109.0 days
Activity this month
13.6 days
Activity this year
14.2 days
Activity to date
14.2 days
Estimate to complete current year
44.6 days
Estimate to complete future years
50.0 days

Project Info

Project
HESA staff return – 15/16
Code
HRS090
Programme
Human Resources (HRS)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
28-Mar-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
25-Nov-2016
Overall Priority
Normal
Category
Compliance