Monthly Progress Report
- Report Date
- April 2016
Achievements:
- Project website set up
- Project start up meeting took place
- Brief completed
- Investigation into HESA requirements
- Design progressed
Issues
- None
Next Steps
- Resourcing for project in progress
- Familiarisation for contractor when has been successfully obtained
- Review design
Milestones
| 22-Apr-2016 | Planning |
| 20-May-2016 | Initial Build |
| 10-Jun-2016 | Initial Acceptance |
| 29-Jul-2016 | First Deployment |
| 30-Sep-2016 | Final HESA return |
| 14-Oct-2016 | Commit |
| 11-Nov-2016 | Final Submission |
| 25-Nov-2016 | Closure |
Project has been given a RAG status of Green
- Approved budget
- 109.0 days
- Activity this month
- 13.6 days
- Activity this year
- 14.2 days
- Activity to date
- 14.2 days
- Estimate to complete current year
- 44.6 days
- Estimate to complete future years
- 50.0 days