Project journal

Title Description Author Post date
Update

21-Sept

Susan is progressing with HESA work, no issues for IS Apps and expects to have submittd to plan before 30-Sept

Anne Mathison 22-Sep-2016
HESA Upload file info of examples from 2014-15

Last year a couple of data files required to be loaded

eg JIRAs HRS085-25 and HRS085-28

Pam S last year prepared scripts and put the completed scripts into the required JIRAs for Dev Tech to Load.

This is just to refer to when we need to do thee same again this year.

  1. Dev review Susan's scripts
  2. Then create a JIRA for HRS090
  3. once created assign to Dev Tech etc as usual
  4. may be required more than once or it may be different files

22-Aug-16

Anne Mathison 11-Aug-2016
First issues have come up on the HESA return 5-Aug

Frist issues have come up onthe HESA return 5-Aug forwarded onto developer on Monday 8=Aug to investigate

The details can be found in JIRA HRS090-9

Anne Mathison 08-Aug-2016
CSG Dev work

 

Anne Mathison 21-Apr-2016
Updates

Updates

  1. HESA Archive completed for 2014-15
  2. ACTQUAL no longer required for HRS090 15-16 return
    1. Pam, I can now confirm we do NOT need the Academic Teaching Qualifications (ACTCHQUAL) added to this year’s return. Susan
  3. Pam handing over HESA knowledge to Ron to allow a handover to  a contractor when he arrives
Anne Mathison 26-Apr-2016
RFC C1604-070

Unidesk - RFC C1604-070

Anne Mathison 21-Apr-2016

Project Info

Project
HESA staff return – 15/16
Code
HRS090
Programme
Human Resources (HRS)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
28-Mar-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
25-Nov-2016
Overall Priority
Normal
Category
Compliance