Report for June 2016

Report Date
June 2016

Achievements in Last Period

  • User Group UAT completed and Signed off on 28 June.
  • Completion of some JIRAs

Issues

  • The Supplier has been unable to deliver a working resolution to JIRA 76 which realtes to security for interview panel members. This has impacted on milestones and the budget split across the two financial years as noted in piccl 11. This has pushed the delivery milestone out by two months due to having to accommodate summer leave across the project team. This is reflected in the project's RED status.

Next Steps

  • Complete JIRA 76 resolution (supplier)
  • Complete JIRA 76 testing in TEST and LIVE (HR Systems)
  • Obtain Special CAB approval for September delivery once confirmation from supplier on JIRA 76

Milestones

09-Sep-2016Completion of prep work on LIVE
16-Sep-2016Completion of TEST Environment/Acceptance Sign-off
28-Sep-2016Delivery
12-Oct-2016Delivery Sign-off
12-Oct-2016Completion of Major Governance Assessment Review
28-Oct-2016Closure

 

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
eRecruitment Upgrade
Code
HRS089
Programme
Human Resources (HRS)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Zoe Lewandowski
Current Stage
Close
Status
Closed
Start Date
09-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Jun-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary