Report for March 2017
- Report Date
- March 2017
Achievements in the last Period
- Delivery signed off by Sponsor, see Delivery sign-off milestone.
- Online survey created to gather feedback from user group members. The survey is based on the success criteria set by the user group in April 2016.
Issues
- Delays to closure, see issue 16.
Next Steps
- Circulate survey
- Project report and closure
- Approved budget
- 182.0 days
- Activity this month
- 1.6 days
- Activity this year
- 58.6 days
- Activity to date
- 175.0 days
- Estimate to complete current year
- 7.0 days
- Estimate to complete future years
- 0.0 days