Report for January 2017

Report Date
January 2017

Achievements in the last Period

  • Minor update (v21.0.23) was installed and tested in TEST by CoreHR and made available to HR for testing on 6 January.
  • HR completed testing and approved the deployment to LIVE which was scheduled to the 24 January to allow for the 2 weeks notice to users.
  • Minor update (v21.0.23) was installed and tested in LIVE by CoreHR on 24 January. Troubleshooting of small issues followed but HR confirmed that all was well on 26 January.
  • All but one Jiras have been closed. Clarification on that last Jira is sought for CoreHR before closing and signing off the delivery.

Issues

  • Delays in update to LIVE means delivery sign-off & closure needs to be pushed back, see issue 15.

Next Steps

  • Confirm resolution of last issue
  • Sign off delivery
  • Decommission old version of application (Dev, Test, Live)
  • Project report and closure

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
182.0 days
Activity this month
5.0 days
Activity this year
53.2 days
Activity to date
169.7 days
Estimate to complete current year
13.6 days
Estimate to complete future years
0.0 days

Project Info

Project
eRecruitment Upgrade
Code
HRS089
Programme
Human Resources (HRS)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Zoe Lewandowski
Current Stage
Close
Status
Closed
Start Date
09-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Jun-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary