Report for January 2017
- Report Date
- January 2017
Achievements in the last Period
- Minor update (v21.0.23) was installed and tested in TEST by CoreHR and made available to HR for testing on 6 January.
- HR completed testing and approved the deployment to LIVE which was scheduled to the 24 January to allow for the 2 weeks notice to users.
- Minor update (v21.0.23) was installed and tested in LIVE by CoreHR on 24 January. Troubleshooting of small issues followed but HR confirmed that all was well on 26 January.
- All but one Jiras have been closed. Clarification on that last Jira is sought for CoreHR before closing and signing off the delivery.
Issues
- Delays in update to LIVE means delivery sign-off & closure needs to be pushed back, see issue 15.
Next Steps
- Confirm resolution of last issue
- Sign off delivery
- Decommission old version of application (Dev, Test, Live)
- Project report and closure
- Approved budget
- 182.0 days
- Activity this month
- 5.0 days
- Activity this year
- 53.2 days
- Activity to date
- 169.7 days
- Estimate to complete current year
- 13.6 days
- Estimate to complete future years
- 0.0 days