Report for October 2016

Report Date
October 2016

Achievements in Last Period

  • BI work was completed and signed off on all three environments
  • The project sponsor agreed to removing the Major Governance Assessment Review as no longer required (noted in issue 12)

Issues

  • Multiple JIRAs remain unresolved since the upgraded version went live. New issues are also being raised with CoreHR support rather than the Upgrades team.
  • Milestones have been rescheduled as noted in Issue 12 but approval for increased budget pending from Business before submitting to WIS.
  • A new PM has been requested to release the current PM to a seconded role given that the project did not close as planned. This will impact the project's budget as any new PM's time will be recorded against the project

Next Steps

  • Obtain approval for additional effort
  • Resolve remaining JIRAs
  • Complete Closure process

 

Milestones

25-Nov-2016 Delivery Sign-off
9-Dec-2016 Closure

 

 

Project Status
RAG Status
Time
RED
Cost
AMBER
Overall
RED
RAG Commentary
The project's Time RAG status is RED because the Closure milestone has been moved out by more than a month. The project's Cost status if AMBER because an increase of 6% is required to deliver the remaining work.
Change Status
Activity
Approved budget
158.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
158.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days

Project Info

Project
eRecruitment Upgrade
Code
HRS089
Programme
Human Resources (HRS)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Zoe Lewandowski
Current Stage
Close
Status
Closed
Start Date
09-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Jun-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary