Report for October 2016
- Report Date
- October 2016
Achievements in Last Period
- BI work was completed and signed off on all three environments
- The project sponsor agreed to removing the Major Governance Assessment Review as no longer required (noted in issue 12)
Issues
- Multiple JIRAs remain unresolved since the upgraded version went live. New issues are also being raised with CoreHR support rather than the Upgrades team.
- Milestones have been rescheduled as noted in Issue 12 but approval for increased budget pending from Business before submitting to WIS.
- A new PM has been requested to release the current PM to a seconded role given that the project did not close as planned. This will impact the project's budget as any new PM's time will be recorded against the project
Next Steps
- Obtain approval for additional effort
- Resolve remaining JIRAs
- Complete Closure process
Milestones
25-Nov-2016 | Delivery Sign-off |
9-Dec-2016 | Closure |
- Approved budget
- 158.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 158.0 days
- Estimate to complete current year
- 11.0 days
- Estimate to complete future years
- 0.0 days