Report for August 2016

Report Date
August 2016

Achievements in Last Period

  • Minor release testing was completed by CoreHR
  • Final HR system testing was completed - this was the minor release which fixed the security issue raised in JIRA 76 on both the DEV and TEST environments
  • Special CAB approval was obtained for the final work on the TEST and LIVE environments
  • Accessiblity testing was completed
  • Final planning and associated resouring confirmed

Issues

  • None

Next Steps

  • Complete prep work on LIVE (stage 1)
  • Complete upgrade of TEST environment (stages 2&3)
  • Complete TEST BI upgrade
  • Complete upgrade of LIVE environment (stages 2&3)
  • Complete LIVE BI Upgrade

 

Milestones

09-Sep-2016Completion of prep work on LIVE
16-Sep-2016Completion of TEST Environment/Acceptance Sign-off
28-Sep-2016Delivery
12-Oct-2016Delivery Sign-off
12-Oct-2016Completion of Major Governance Assessment Review
28-Oct-2016Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
eRecruitment Upgrade
Code
HRS089
Programme
Human Resources (HRS)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Zoe Lewandowski
Current Stage
Close
Status
Closed
Start Date
09-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Jun-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary