Report for July 2016

Report Date
July 2016

Achievements in Last Period

  • All issues, with the exception of JIRA 76, have been resolved and re-tested
  • Fix for remaining issue, JIRA 76, has been applied to the DEV environment and final checks by Supplier are in progress ahead of HR systems completing their final testing on DEV and TEST.
  • Accessibility testing of v21 has been scheduled to take place on 23 August.
  • Budget has been reduced by 7 days to 158 days: this reflects PM time no longer being recorded against the proejct being offset against the additional work that has been required to support the resolution of the JIRAs in DEV and TEST. There is more effort being continued into 16/17 than originally planned.
  • Demo of TestRail to IS Senior Supplier and Head of Development Services was positively received and IS Applications will be pursuing implementing this type of software as another success factor in projects.

Issues

  • None

Next Steps

  • Minor release testing to be completed by CoreHR
  • Final HR System testing - minor release for JIRA 76 fix on DEV and TEST
  • Special CAB approval for delivery date to be requested
  • Accessibility testing to be completed

 

Milestones

05-Aug-2016Final testing by HR Systems
09-Sep-2016Completion of prep work on LIVE
16-Sep-2016Completion of TEST Environment/Acceptance Sign-off
28-Sep-2016Delivery
12-Oct-2016Delivery Sign-off
12-Oct-2016Completion of Major Governance Assessment Review
28-Oct-2016Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
eRecruitment Upgrade
Code
HRS089
Programme
Human Resources (HRS)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Zoe Lewandowski
Current Stage
Close
Status
Closed
Start Date
09-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Jun-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary