- Report Date
- September 2015
Achievements in Last Period
- TR code raised following August's approval for funding
- Brief draft in progress
Issues
- Planning sign-off rescheduled due to resource conflict for PM's time. This has not impacted the overall delivery timescales for the project
Next Steps
- Complete Supplier readiness stage
- Complete Brief, including review and update of plan and 3pt estimate
- Secure all project resources
- Establish refreshed User Group
- Schedule project's Board and User Group meetings
Milestones
- Approved budget
- 120.0 days
- Activity this month
- 4.3 days
- Activity this year
- 4.6 days
- Activity to date
- 4.6 days
- Estimate to complete current year
- 107.3 days
- Estimate to complete future years
- 8.0 days