Report for September 2015

Report Date
September 2015

 Achievements in Last Period

  • TR code raised following August's approval for funding
  • Brief draft in progress

Issues

  • Planning sign-off rescheduled due to resource conflict for PM's time. This has not impacted the overall delivery timescales for the project

Next Steps

  • Complete Supplier readiness stage
  • Complete Brief, including review and update of plan and 3pt estimate
  • Secure all project resources
  • Establish refreshed User Group
  • Schedule project's Board and User Group meetings

Milestones

09-Oct-2015Planning Sign-off
01-Aug-2016Delivery
30-Sep-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
4.3 days
Activity this year
4.6 days
Activity to date
4.6 days
Estimate to complete current year
107.3 days
Estimate to complete future years
8.0 days

Project Info

Project
eRecruitment Upgrade
Code
HRS089
Programme
Human Resources (HRS)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Zoe Lewandowski
Current Stage
Close
Status
Closed
Start Date
09-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Jun-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary