Monthly Progress Report

Report Date
October 2015

Achievements This Period

  • HR handled any queries required for the return
  • HESA made the return 'Credible' on 30th Oct

Issues

  • None

Next Steps

  • Director of HR required to sign off return
  • Closure written
  • Project Closed.

Milestones

12-Nov-2015Final Submission
27-Nov-2015Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
0.9 days
Activity this year
6.3 days
Activity to date
48.1 days
Estimate to complete current year
10.8 days
Estimate to complete future years
0.0 days

Project Info

Project
HESA Staff Return 14/15
Code
HRS085
Programme
Human Resources (HRS)
Project Manager
Anne Mathison
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
23-Mar-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Nov-2015
Overall Priority
Normal
Category
Compliance