June Progress Report

Report Date
June 2015

Achievements This Period

  • The last item in Build has been completed and moved to test
  • Archive data required to be carried through to LIVE before any 2014-15 return work proceeded to Live has been done
  • Acceptance testing of known work briefly tested in order to implement to Live .
  • Initial Acceptance milestone approved
  • Staff Return implemented to Live on 29-Jun-15

Issues

  • None

Next Steps

  • HESA testing at this point is the testing of the known identified HESA work
  • Now that the Staff Return has been implemented to Live on 29-Jun-15 this enables testing with real data to start to take place. However it will only provide initial testing as much of the testing has to wait until August

Milestones

31-Jul-2015Start of Deployment
30-Sep-2015First HESA Return
15-Oct-2015Commit
12-Nov-2015Final Submission

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
70.0 days
Activity this month
4.6 days
Activity this year
26.4 days
Activity to date
26.4 days
Estimate to complete current year
11.2 days
Estimate to complete future years
20.4 days

Project Info

Project
HESA Staff Return 14/15
Code
HRS085
Programme
Human Resources (HRS)
Project Manager
Anne Mathison
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
23-Mar-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Nov-2015
Overall Priority
Normal
Category
Compliance