June Progress Report
- Report Date
- June 2015
Achievements This Period
- The last item in Build has been completed and moved to test
- Archive data required to be carried through to LIVE before any 2014-15 return work proceeded to Live has been done
- Acceptance testing of known work briefly tested in order to implement to Live .
- Initial Acceptance milestone approved
- Staff Return implemented to Live on 29-Jun-15
Issues
- None
Next Steps
- HESA testing at this point is the testing of the known identified HESA work
- Now that the Staff Return has been implemented to Live on 29-Jun-15 this enables testing with real data to start to take place. However it will only provide initial testing as much of the testing has to wait until August
Milestones
31-Jul-2015 | Start of Deployment |
30-Sep-2015 | First HESA Return |
15-Oct-2015 | Commit |
12-Nov-2015 | Final Submission |
- Approved budget
- 70.0 days
- Activity this month
- 4.6 days
- Activity this year
- 26.4 days
- Activity to date
- 26.4 days
- Estimate to complete current year
- 11.2 days
- Estimate to complete future years
- 20.4 days