Monthly Progress Report

Report Date
May 2015

Achievements This Period

  • Design milestone approved
  • Archive data for 2013-14 completed including adding the 3 new fields required for that archive year
  • Archive data complete in Dev and has been carried through to Test.
  • The majority of the Build work has been completed in May bar one awaiting testing to checked out in Test to describe the requirement
  • Initial Build work complete

Issues

  • None

Next Steps

  • Archive data requires to be carried through to LIVE before any 2014-15 retrun work proceeds to Live
  • HESA testing will get underway in June and proceed to Live as soon as possible to allow real testiong to be undertaken
  • HESA testing at this point is the testing of the known identified HESA work

Milestones

26-Jun-2015Initial Acceptance
31-Jul-2015Start of Deployment
30-Sep-2015First HESA Return
15-Oct-2015Commit
12-Nov-2015Final Submission
27-Nov-2015Closure
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
70.0 days
Activity this month
12.2 days
Activity this year
21.8 days
Activity to date
21.8 days
Estimate to complete current year
25.0 days
Estimate to complete future years
20.1 days

Project Info

Project
HESA Staff Return 14/15
Code
HRS085
Programme
Human Resources (HRS)
Project Manager
Anne Mathison
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
23-Mar-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Nov-2015
Overall Priority
Normal
Category
Compliance