Update on 20-Aug

Update on 20-Aug

Susan McL progressing with testing and checking items out, not expecting any work for Pam S  until Sept.

This is due to extra validation carried out in the early validation in HESA, which has already been resolved.

Susan McL has 50 cases that she will have to manually work through, but does not expect Pam to have to complete any fixes. If data corrections comes up there may be Apex work, but that can be looked at at the time if required.

At present all good

 

Pam S on holiday from 31-Aug back 17th Sept

Susam Mcl on hol 7-18 Sept back on 14th.

 

Contingency if Susan McL has an issue will try John C

Project Info

Project
HESA Staff Return 14/15
Code
HRS085
Programme
Human Resources (HRS)
Project Manager
Anne Mathison
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
23-Mar-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Nov-2015
Overall Priority
Normal
Category
Compliance