June 2015

Report Date
June 2015

Achievements in last period

  • Completed business requirements workshops with all 4 user groups: UHRS, College devolved HR, and both School and Support Groups

Issues

  • Revised estimates, issue: new estimates are 50d (was 35d). Agreed 2d contingency will be used within the programme and 5 d from the HR Hesa project.
  • Agreed milestones to move to 15/16 for the requirements sign offs and closure, to take into account the additional consultation work and holidays (https://www.projects.ed.ac.uk/project/hrs084/issues/7)

Next Steps

  • Prioritise the mandatory requirements with Senior Users
  • Complete some of the outstanding analysis and adress details of the prioritsed requirements

 

01-Sep-2015Business Requirements Document reviewed and signed off
11-Sep-2015Close
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
35.0 days
Activity this month
13.6 days
Activity this year
43.5 days
Activity to date
43.5 days
Estimate to complete current year
3.7 days
Estimate to complete future years
3.5 days

Project Info

Project
Enhancing Employment Analysis
Code
HRS084
Programme
Human Resources (HRS)
Project Manager
Franck Bergeret
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
24-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Feb-2016
Programme Priority
2
Category
Discretionary