May 2015
- Report Date
- May 2015
Achievements in last period
- Completed the curent process review with Devolved Support Groups , and SCE/MVM Devolved Business Groups
- Current processes signed off
- Completed 1st business requirements workshops with all 4 user groups: UHRS, College devolved HR, and both School and Support Groups
Issues
- Revised estimates, issue: new estimates are 40d (was 35d). Agreed 2d contingency will be used within the programme.
Next Steps
- Complete the business requirements workshops
- Review and prioritise the requirements with Senior Users
06-Jul-2015 | Business Requirements Document reviewed and signed off |
16-Jul-2015 | Close |
- Approved budget
- 35.0 days
- Activity this month
- 11.0 days
- Activity this year
- 29.9 days
- Activity to date
- 29.9 days
- Estimate to complete current year
- 10.6 days
- Estimate to complete future years
- 0.0 days