May 2015

Report Date
May 2015

Achievements in last period

  • Completed the curent process review with Devolved Support Groups , and SCE/MVM Devolved Business Groups
  • Current processes signed off
  • Completed 1st business requirements workshops with all 4 user groups: UHRS, College devolved HR, and both School and Support Groups

Issues

  • Revised estimates, issue: new estimates are 40d (was 35d). Agreed 2d contingency will be used within the programme. 

Next Steps

  • Complete the business requirements workshops 
  • Review and prioritise the requirements with Senior Users

 

06-Jul-2015Business Requirements Document reviewed and signed off
16-Jul-2015Close
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
35.0 days
Activity this month
11.0 days
Activity this year
29.9 days
Activity to date
29.9 days
Estimate to complete current year
10.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Enhancing Employment Analysis
Code
HRS084
Programme
Human Resources (HRS)
Project Manager
Franck Bergeret
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
24-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Feb-2016
Programme Priority
2
Category
Discretionary