Achievements in last period

  • brief sign off
  • started consultation with stakeholders: review of the current processes for managing, reporting Guaranteed Hours

Issues

  • none

Next Steps

  • Confirm list of stakeholders to take part into requirements gathering over workshops over the 3 levels: UHRS, Devolved Support Groups, and Devolved Business Groups
  • Sign off current processes

 

02-Apr-2015Brief Sign Off
08-May-2015Sign off current Processes
06-Jul-2015Business Requirements Document reviewed and signed off
16-Jul-2015Close

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Enhancing Employment Analysis
Code
HRS084
Programme
Human Resources (HRS)
Project Manager
Franck Bergeret
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
24-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Feb-2016
Programme Priority
2
Category
Discretionary