March 2015
- Report Date
- March 2015
Achievements in last period
- brief sign off
- started consultation with stakeholders: review of the current processes for managing, reporting Guaranteed Hours
Issues
- none
Next Steps
- Confirm list of stakeholders to take part into requirements gathering over workshops over the 3 levels: UHRS, Devolved Support Groups, and Devolved Business Groups
- Sign off current processes
02-Apr-2015 | Brief Sign Off |
08-May-2015 | Sign off current Processes |
06-Jul-2015 | Business Requirements Document reviewed and signed off |
16-Jul-2015 | Close |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days