January 2016
- Report Date
- January 2016
Achievements in Last Period
- Final actions on the requirements completed: feedback from Payroll, Support user group and Business Lead were alll added to the requirements, which have been redistributed to project sponsor.
Issues
- the project is AMBER as there has been delay in getting and adding all remaining feedback to the final version of the requirements
Next Steps
- Sponsor to agree final version of the requirements
- Close
01-Feb-2016 | 14-Jan-2016 | Business Requirements Document reviewed and signed off | Analyse | No | edit | view |
15-Feb-2016 | 21-Jan-2016 | Close |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days