Report for December 2015

Report Date
December 2015

Achievements in Last Period

  • The final requirements were reviewed with Programme Owner, Project Sponsor and Business Lead. This review agree which requirements are externally compliant and which are internally compliant and those that are not compliant. There are some final actions arising from the final review meeting which, together with annual leave, meant final sign-off is postponed to 14 January

Issues

  • Delivery milestone rescheduled to accommodate final actions on requirements as noted in piccl 17 and is the reason for the project's AMBER status

Next Steps

  • Complete final actions on requirements
  • Close

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Enhancing Employment Analysis
Code
HRS084
Programme
Human Resources (HRS)
Project Manager
Franck Bergeret
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
24-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Feb-2016
Programme Priority
2
Category
Discretionary