November 2015

Report Date
November 2015

Achievements in last period

  • Requirements were reviewed with the whole user group
  • Opened issues reported in piccl 12 have been solved
  • Paternity Leave process solved

Issues

  • Additional effort reported and agreed piccl 15
  • Additional delay for final sign off due to additional work and annual leaves from senior users piccl16
  • The project is Red as the closure has moved to more than a month. The Cost has also increased and is Amber. Both issues have been solved. 

Next Steps

  • Complete the sign off of the prioritised requirements by senior users 

 

18-Dec-2015Business Requirements Document reviewed and signed off
21-Jan-2016Close
Project Status
RAG Status
Time
RED
Cost
AMBER
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
73.0 days
Activity this month
9.0 days
Activity this year
15.0 days
Activity to date
68.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Enhancing Employment Analysis
Code
HRS084
Programme
Human Resources (HRS)
Project Manager
Franck Bergeret
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
24-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Feb-2016
Programme Priority
2
Category
Discretionary