November 2015
- Report Date
- November 2015
Achievements in last period
- Requirements were reviewed with the whole user group
- Opened issues reported in piccl 12 have been solved
- Paternity Leave process solved
Issues
- Additional effort reported and agreed piccl 15
- Additional delay for final sign off due to additional work and annual leaves from senior users piccl16
- The project is Red as the closure has moved to more than a month. The Cost has also increased and is Amber. Both issues have been solved.
Next Steps
- Complete the sign off of the prioritised requirements by senior users
18-Dec-2015 | Business Requirements Document reviewed and signed off |
21-Jan-2016 | Close |
- Approved budget
- 73.0 days
- Activity this month
- 9.0 days
- Activity this year
- 15.0 days
- Activity to date
- 68.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days