Monthly Progress Report

Report Date
September 2014

Achievements This Period

  • Supported any reported bugs
  • Two urgent bugs arrived 24th Sept and 29th Sept requiring scripts to assist HR clean up the data. JIRA HRS082-46 relating to 700 DATEFHEI with incorrect values and JIRA HRS082-47 relating to 541 ACEMPFUN staff with the wrong codes that required fixed before the return will be finally submitted to HESA.  These 2 items corrected data is now successfully visible on the APEX report  for the 2013-14 HESA Staff  Return
  • These 2 items( DATEFHEI , ACEMPFUN) will be input as requirements for the 2014-15 HESA Staff Return project to find permanent solutions. 

Issues

  • None

Next steps

  • Support any reported bugs if they require any data changes that require scripts
  • HR will commit 2013-14 HR HESA return on 15-Oct-14
  • Closure will follow by end of October

Current Milestones

DateMilestone
31-Oct-2014HR Staff Return Close

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
88.0 days
Activity this month
7.5 days
Activity this year
19.5 days
Activity to date
88.5 days
Estimate to complete current year
1.5 days
Estimate to complete future years
0.0 days

Project Info

Project
HR HESA Staff Return 2013/14
Code
HRS082
Programme
Human Resources (HRS)
Project Manager
Anne Mathison
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
10-Apr-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
23-Oct-2014