Report for July 2014
- Report Date
- July 2014
Achievements this period
Funding confirmed for 14/15 patching with caveat that days to be used by end September
Milestones replanned and resources secured for AE and RTI functional patches
Autoenrolement patch applied to DEV without issue
Outstanding Issues
N/A
Next steps
Confirm acceptance of AE patching in TEST
Progress RTI Patching to DEV and TEST
Undertake UAT for AE and RTI patches
Apply both patches to LIVE
Deployment and Closure
| 13-Aug-2014 | RTI DEV - Patching sign off |
| 19-Aug-2014 | Autoenrolment and RTI Patching - TEST Sign off |
| 27-Aug-2014 | AE and RTI LIVE Patching |
| 12-Sep-2014 | Deployment Sign off and Closure |
- Approved budget
- 50.0 days
- Activity this month
- 2.0 days
- Activity this year
- 35.0 days
- Activity to date
- 35.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 15.0 days