Report for February 2014
- Report Date
- February 2014
Achievements this period
- LIVE cloned to TEST
- Payroll and FIS completed configuration changes suggested by Oracle Consultant
Outstanding Issues
- Project Brief to be finalised and approved
Next steps
- Continue support of RTI balance reports currently timing out
- Continue to support the RTI end of year and monthly processes as required by Payroll
| 07-Mar-2014 | 07-Mar-2014 | Planning Sign Off |
| 17-Apr-2014 | 17-Apr-2014 | HMRC Deadline for completion of End of Year processes |
| 25-Apr-2014 | 25-Apr-2014 | Review Budget and Prioritise Autoenrollment Enhancements |
| 30-May-2014 | 30-May-2014 | Closure |
- Approved budget
- 30.0 days
- Activity this month
- 9.0 days
- Activity this year
- 10.0 days
- Activity to date
- 10.0 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 0.0 days