Project journal

Title Description Author Post date
JRE 1.7 patches

Met with Gillian to review JRE 1.7 patches and estimates

Decided investigation to JRE and Security patches can start 4th Feb week, leaving a gap of a week whilst Gillian if off an extra day.

 

Some revision of estimates an extra 3 days, project can accommodate

Anne Mathison 31-Jan-2013
ASOR Testing

Kathy completed testing on Friday 18th Jan, however few errors raised, 2 with Oracle which may prevent/delay the P1 LIVE deployment

Anne Mathison 21-Jan-2013
Progress

Niether HR or Payroll have started testing this week yet. HR have to set up some data.

Payroll have been completing autoenrolment reports in Dev.

Kathy is planning to start this week and expects to have work complete in Test by the 17th.

Anne Mathison 08-Jan-2013
P1 Patches in Test complete during afternoon of 19th Dec.

P1 Patches in Test complete  during afternoon of 19th Dec.

 Now ready for Acceptance testing to start - email sent out by Ana and I have requested JIRA to be set up.

Anne Mathison 19-Dec-2012
Clone to Dev - hit issue

We've hit an error with the clone. Hopefully this will be straightforward to resolve I've opened SR with Oracle to verify how to resolved.

 SR 3-6519660351

 Gordon will monitor this and I'll pick this up when I return on Thursday.

 

 

Anne Mathison 04-Dec-2012
Reviewed P1 estimates with AE and GF

Some estimates adjusted and amended the P1 UAT milestone from 11th Jan to 17th Jan, no impact on other dates

Anne Mathison 28-Nov-2012
HRS072 Brief

Attaching FIN082 ToR and adding Milestones and Risks to this project . Include in an added new page and call it the Brief discussed at 1 to 1 with Rhian - to do

Anne Mathison 29-Oct-2012
Infrastructure downtimes information

https://www.wiki.ed.ac.uk/display/insite/Applications+Division+Infrastructure

 

Anne Mathison 22-Nov-2012