Report for May 2013

Report Date
May 2013
 
Achievements in last period:

UAT sign-off confirmed for HR database and application changes.

HR database and application changes deployed to Live. 

UAT sign-off confirmed for HESA Apex forms and BOXI Universes.

UAT sign-off confirmed for eRecruitment extract.

Issues:

By the morning of the UAT sign-off meeting, not all of the UAT testing had been completed.  This resulted in delays to the Acceptance sign-off, Delivery, and Delivery sign-off milestones.

An additional deployment delay will also be required, for the eRecruitment extract changes only.  This is to allow more time for HR to load the new ACTSOC values into eRecruitment.  

Next Steps:

Final UAT sign-off for HESA changes to be confirmed.

HESA changes to be deployed to Live.

HR to load new ACTSOC values, and make the new ACTSOC fields "active", in eRecruitment.

eRecruitment extract to be deployed to Live. 

Deployment sign-off to be confirmed.

Remaining Milestones:

07-June-2013HESA Acceptance sign-off

14-June-2013

28-June-2013 (? - tbc by HR)

HESA Delivery

eRecruitment Delivery

26-Jun-2013Delivery sign-off
15-Nov-2013Post-deployment sign-off
13-Dec-2013Closure

      

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
264.0 days
Activity this month
28.0 days
Activity this year
201.0 days
Activity to date
201.0 days
Estimate to complete current year
22.0 days
Estimate to complete future years
40.0 days

Project Info

Project
HR HESA Staff Return 12/13
Code
HRS071
Programme
Human Resources (HRS)
Project Manager
Nikki Stuart
Project Sponsor
Sheila Gupta
Current Stage
Close
Status
Closed
Start Date
24-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Dec-2013
Programme Priority
1
Overall Priority
Higher
Category
Compliance