Report for January 2013

Report Date
January 2013
Achievements in last period:

Business Requirements Document created and approved

It was agreed at the Business Analysis Review meeting that there is a potential to deliver in a phased approach, with the changes to the HR database and application being released ahead of the rest of the deliverables.  This would allow HR more time to input data into the new HR fields.

Four Design stage meetings have been held with the key business stakeholders

The System Design is progressing well

A new Configuration Team member has been recruited to take forward a significant portion of the Build work

A development request form has been submitted to the Configuration Team manager, for another new team member to attend a training course on the new software tool that will be used to redevelop the HESA forms.

Issues:

The Systems Designer has a great many other demands on her time, for example recruitment and mentoring of new team members.  This has impacted the time she has had available for project work.  Consequently, the Configuration Team Manager has advised that she should now be bookable only to 56% fte.  This has resulted in a milestone delay to the Design stage, and may have a knock-on impact on subsequent milestones.

Next Steps:

System Design to be completed and approved

Estimates to be reviewed, and project re-planned to reflect any changes

 

Remaining Milestones:

 

08-Feb-2013System Design sign-off
05-Apr-2013Build sign-off
22-Apr-2013Integration sign-off
22-May-2013Acceptance sign-off
30-May-2013Delivery
19-Jun-2013Delivery sign-off
15-Nov-2013Post-deployment sign-off
13-Dec-2013Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
264.0 days
Activity this month
29.0 days
Activity this year
37.0 days
Activity to date
37.0 days
Estimate to complete current year
187.0 days
Estimate to complete future years
40.0 days

Project Info

Project
HR HESA Staff Return 12/13
Code
HRS071
Programme
Human Resources (HRS)
Project Manager
Nikki Stuart
Project Sponsor
Sheila Gupta
Current Stage
Close
Status
Closed
Start Date
24-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Dec-2013
Programme Priority
1
Overall Priority
Higher
Category
Compliance