- Report Date
- November 2019
Achievements this Period
- The upgrade to the Test system has been completed
- User Acceptance Testing has commenced
- Initial checks have been completed with no problems reported
- HR integration tests have been successfully completed
Issues
- A delay has been experienced in completing the upgrade due to a combination of the following reasons;
- Technical Lead time restricted due to other project priorities
- Unexpected issues encountered during the upgrade process, requiring supplier input on a few occasions
- Industrial action
- The Mjog sms txt messaging service has not been installed due to delays in confirming the commercials
- The Single Sign-On (SSO) for the portal has not been configured due to holidays and Industrial action
- Reduced time for testing will result in not completing the UAT according to the original schedule
- As a result of the delays, the project has been re-planned after discussions with the business team
-
Next Steps
- Complete UAT on the Test system
- Install the Mjog sms txt messaging service
- Configure Single Sign-On (SSO) for the portal
- Approved budget
- 50.0 days
- Activity this month
- 2.1 days
- Activity this year
- 7.3 days
- Activity to date
- 7.3 days
- Estimate to complete current year
- 33.0 days
- Estimate to complete future years
- 0.0 days
This article was published on